Almost every serious inquiry contains the same sentence somewhere: "what is your delivery time?" It is asked early because a rig that arrives after the dry season is worth less than one that arrives before it. The trouble is that a single figure answers a question nobody actually asked. A rig does not have a lead time; it has a schedule, and only part of that schedule belongs to the factory.
Five stages, five different owners
A core drilling rig reaches site through fabrication, assembly, load testing, export packing and sea freight. Each stage is controlled by somebody different — the factory, the inspector, the forwarder, the shipping line — and quoting one number for all five is how projects slip. The buyer plans against a production figure, the supplier meant working days, and nobody counted the time on water.
| Stage | What happens | What controls how long it takes |
|---|---|---|
| Fabrication | Frame, mast, skid or crawler chassis cut, welded, machined and painted | Whether the model is in the current production programme or built to order; steel and casting availability; any non-standard dimension |
| Assembly and plumbing | Engine, hydraulic circuit, winch, rotation head, control panel | Whether the hydraulic layout is standard or re-plumbed around a specified brand |
| Load test and adjustment | Run-in under load, pressure and flow checks, wireline winch calibration | How many items need correction on the first run; whether a third-party witness is required |
| Export packing | Diesel drained, rust protection, crate or frame, container loading | Crate or fumigation requirements, and whether the buyer books his own inspection before packing |
| Sea freight | Port to port, then inland to site | Route, sailing frequency and season — not the factory |
Why this article does not give you a number
Because a number published on a website has to fit every specification, every season and every destination, and it cannot. A standard skid rig that a factory builds continuously and a crawler rig with a specified engine brand, an extra hydraulic circuit and a customer paint scheme are not the same object, even when they share a model name. The first can be scheduled against an existing build slot. The second starts with a mast and a chassis that are made for that order.
What a supplier can do is give you a schedule with a date against each stage, in the proforma invoice, before you pay the deposit. Ask for that. A supplier who will not put stage dates in writing is telling you the lead time is a sales number, not a production plan.
Standard model versus built-to-order
The difference is structural, not administrative. On a standard model the deviations are chosen from a list: which chuck, which rod length, which engine from the approved options. On a built-to-order machine the deviation runs back into the drawing — the mast height, the mounting pattern, the hydraulic routing. Every deviation from the standard specification adds time, and the additions do not scale evenly. A different engine brand means re-plumbing and re-checking the control logic. A non-standard rod size means work at the rotation head and chuck. A specified brand of hydraulic pump may mean waiting for an import the factory does not control.
This is why the most useful thing a buyer can do before asking for a date is to freeze the specification. "Hydraulic chuck, three-metre rod, this engine" is buildable and schedulable. "Your standard model, but better" is not.
Why "in stock" and "ready to ship" are not the same
Some suppliers list rigs as in stock. Ask two follow-up questions before you treat that as a schedule: is the machine assembled and load tested, and are the export documents already prepared? An assembled rig with no inspection record still needs a run-in and a packing cycle. A machine that has been standing in a yard also needs its hydraulic oil, seals and battery checked before it goes under load — and a rig that fails that check costs more time than one that was never called "in stock".
What actually shortens the wait
- Place the deposit against a frozen specification, not a range.
- Book the sailing before the rig is finished. Space on the long routes tightens around major holidays, and a finished rig waiting for a slot looks exactly like a rig that was never built.
- Ask for the inspection pack in parallel with production: photographs of the load test, gauge readings, the bill of lading draft, the packing list. Every document you approve early is a delay you do not inherit after the container is sealed.
- Agree the Incoterm explicitly. FOB and CIF differ by more than insurance — they decide who books the space, and therefore who owns the calendar.
- Agree whether the quoted schedule is in calendar days or working days, and when the clock starts: deposit, drawing approval, or steel release. Most arguments about a late rig are arguments about the start date.
How to plan with a schedule instead of a number
Put the stage dates in front of your own client, not a single figure. If the rig is for a programme with a fixed start, work backwards: site assembly and commissioning first, then inland transport and clearance, then the sailing, then packing and inspection, and only then production. What remains is the production window the factory has to hit — and that is the only part you can negotiate.
If a quoted lead time looks dramatically shorter than the stage schedule implies, the useful question is not "why so fast" but "which stage are you not counting". Sometimes the answer is genuinely good: the factory builds this model continuously and has a unit on the line. Sometimes the answer is that shipping, inspection or packing is not included.
If you would rather have a schedule than a promise, send the specification you intend to freeze and the destination port — the reply comes back with a date against each stage.